Cameby Downs Coal Mine
Peter Campbell Earthmoving has been contracted by Syntech Resources to carry our civil earthworks for the new Cameby Downs Coal Mine between Miles and Chinchilla in the Surat Basin, West of Brisbane.
Due to the short construction timeframe and engineering issues, Peter Campbell Earthmoving entered into a Service Agreement of which budgets and KPI’s were agreed for each section of work. To date, Peter Campbell Earthmoving has completed:
- Site Road Construction
- Drainage
- All earthworks for the CHPP and Train Loadout
- ROM area (250,000 BCM)
- Dirty Water Dam (620,000 bcm)
- Raw Water Dam (100,000 bcm)
Current works include the 9 Km Rail Loop, Rejects Starter Dam (320,000 bcm) and a second Dirty Water Dam (70,000bcm)
Project Duration: 12months+
Project Cost: $20M
Watpac Civil infrastructure Talinga Water Treatment Facility (Origin Gas)
Origin Energy required the construction of a Water Treatment Facility, Effluent Pond and Feed Pond in order to facilitate its Coal Seam Gas (CSG) operations in the Talinga region. Water extracted during the CSG process is treated, filtered and re-processed to enable both commercial and non-commercial uses. Peter Campbell Earthmoving supplied Scrapers, Dozers, Graders, Excavators, Rollers, Articulated Trucks and more to the project which was managed by Watpac Civil.
Project Duration: 5 Months
Project Value: $2M